| ° Home ° Forums ° Reply ° Statistics ° Sign Up ° Search ° Manual ° |
| PM forums / Developing GanttPV / GanttPV v0.9 Beta: Resource dialog doesn't display identical last names |
| Author | Message |
| richard Member |
# Posted: 15 Apr 2008 11:07:58 - In my resource report defined at the All Projects level, I have two resources with identical last names. Only one of the names appears in the dialog list box, however, when I want to assign a resource by clicking the Assign Resource button on the command bar in a task report. The only workaround seems to be to add a distinguishing character to the entries in field concerned under the Name column of the Resource report. It would be better to have the Assignment dialog display last and first names, and possibly the corresponding unique ID for the resource to resolve any identical first names, to be displayed in an order and according to a sort mode that can be freely defined by the user. |
| richard Member |
# Posted: 15 Apr 2008 11:58:15 - Further to my previous post, after stopping and restarting the program, then removing (via Remove Dependencies script) and reapplying depencies to child tasks listed under a parent, the parent color bar appeared and adjusted dynamically as expected. |
| Alexander Moderator |
# Posted: 25 Apr 2008 10:33:59 - Good point, Richard. Thanks. |
| Alexander Moderator |
# Posted: 14 May 2008 21:13:54 - Richard, I've committed the change for GanttPV v0.10. The dialog will display last and first names, and resources with identical names will be displayed together in the order of their IDs. |
|
Powered by mini BB forum software © 2001-2010 |